Call Us: 614.875.9023

Chemistry Biomolecular Engineering Building (CBEC)

The CBEC project was on a tight schedule and postage stamp jobsite. The coordination process for the CBEC project was a challenge because the model did not take into account the insulation of the mechanicals. We caught this and had to reroute and re-coordinate the mechanicals without affecting the building process. Our prefabrication scheduling allowed us to make “just in time” deliveries to accommodate the job site size.

Project Information
Services Provided: HVAC Piping, Duct, Lab Exhaust, High Purity Lab Gases, DI Water System, Plumbing
Project Schedule (Design+Construction): March 2012–September 2014
Completion Date: October 2014
Total Construction Value: $126,000,000
Description: 225,000 sq ft Laboratory Project
Subcontract Type: Lump Sum Negotiated CMR
Original Contract Value: $23,841,000
Final Contract Value: $25,000,000

 

Client:The Ohio State University