Construction for The Hollywood Casino started several months before the construction documents were completed so coordination was started at 60% documents. Within 5 months of award, the permanent heating system was in operation. The completion date was 2 months ahead of schedule.
Project Information |
---|
Services Provided: HVAC Piping, Duct and Plumbing |
Project Schedule (Design+Construction): January 2011–October 2012 |
Completion Date: October 2012 |
Total Construction Value: $195,744,000 |
Description: Casino/Restaurant Parking Garage Central Plant |
Subcontract Type: Design Assist CMR GMP Audited |
Original Contract Value: $31,168,999 |
Final Contract Value: $29,514,458 |
Client:Penn Gaming